Hegar Road at Spring Creek - Bridge replacement project, removal and replacement of bridge.
Kluge from north of Huffmeister to McSwain - Construction of a 4-lane concrete boulevard. 99 percent complete.
Kluge from McSwain to the Precinct Line - Construction of a 4-lane concrete boulevard. 1 percent complete.
Mueschke from Little Cypress to Huffmeister - Conatruction of a 4-lane concrete boulevard. 10 percent complete.
Schiel from Mueschke to 1/2 mile west - Construct a 4-lane concrete boulevard. 60 percent complete.
Skinner from Spring Cypress to Huffmeister - Construct a 4-lane concrete boulevard. 45 percent complete.
Completed Projects Traffic Projects