PROJECT |
DESCRIPTION |
STATUS |
ESTIMATED COMPLETION DATE |
Aldine Mail Route -
Airline to Aldine Westfield
Key Map 413E |
Construction of a 4-lane
concrete divided
roadway,
with traffic signal upgrades. |
Design |
2012 |
Beamer Road -
From Dixie Farm to F.M. 528
Key Map 616M |
Provide a preferred route
for schematic design of the Beamer Road extension from
Dixie Farm Road to F.M. 528 |
Preliminary Engineering |
Undetermined |
Beamer Road -
From Dixie Farm to West Bay Area Blvd.
Key Map 616M |
Proposed 4-lane concrete divided roadway with
traffic signal upgrades, storm sewer and drainage improvements. |
Preliminary Engineering |
Undetermined |
Blackhawk Boulevard at Beltway 8
Key Map 575Z |
Left Turn Lane Design
Right Turn Lane Design |
Design
Design |
2010
2011 |
C.E. King Parkway at US 90A
Key Map 456M |
Widen existing 2 lane asphalt
roadway to a 4-lane
concrete roadway; completing boulevard section across
railroad. |
Construction |
2011 |
C.E. King Parkway -
Tidwell to Beaumont Highway
Key Map 456C |
Construction of a 4-lane concrete
divided roadway with storm sewers, traffic signals and
twin bridges. |
Complete |
2006 |
Constitution Lane
Pedestrian Bridge
Key Map 617X |
Design /Construct a
Pedestrian Bridge |
Design |
2011 |
Cullen Boulevard -
From Almeda-Genoa Road to BW8
Key Map 573S |
Design/Construct 4-lane divided
concrete roadway. |
Preliminary Engineering |
2011 |
Dixie Farm Rd.
-
Clear Creek to Beamer
Key
Map
616Q |
Joint participation
with TXDOT and the City of Pearland for construction of
a 4-lane concrete boulevard. |
Complete |
2008 |
East Mount Houston -
from BW8 to Mesa Road
Key Map 415K |
Design a 4-Lane
Concrete Roadway including Bike Paths |
Preliminary Engineering |
2011 |
East Mount Houston -
from BW8 to Mesa Road
Key Map 415K |
Widen existing 2-lane
asphalt roadway to 4 lane concrete roadway. |
Preliminary Engineering |
2011 |
El Dorado Blvd. -
Beamer Road to Blackhawk Blvd.
Key Map 617U |
Proposed 4-land divided concrete roadway
with storm sewer and traffic signal upgrades. |
Complete |
2010 |
Ella Blvd.(Wheatley) from Little York to West
Gulf Bank
Key Map 412M |
Design a 4-Lane Concrete
Roadway with Storm Sewers.
(City of Houston managed project) |
Design |
2012 |
Gulf Bank at Sweetwater Lane
Key Map 412M |
Provide drainage, left turn lane
and traffic
signal improvements. |
Design |
2011 |
|
|
|
|
|
Hughes Road
From Sageblossom to
Pearland City Limits
Key Map 616E |
Design/Construct a 4-Lane divided
concrete roadway, including bridges over HCFCD drainage ditch.
|
Design
|
2011 |
Hutcheson Park Hike and Bike Trail
(IH 610 at Lockwood)Key
Map 454U |
Provide fitness court, exercise
equipment, sidewalks and improve drainage within park. |
Design |
2010 |
Imperial Valley
From Rankin to Harvest Time Lane
Key Map 372M |
Design/Construct a 4-Lane
divided
concrete roadway. |
Construction |
2011 |
Orem
Drive - Phase IA Telephone to E. of Mykawa Rd.
Key Map 574R |
Joint participation with the City of Pearland in the construction
of a 4-lane concrete roadway and bridge with storm
sewers and traffic signals. |
Complete |
2006 |
Scarsdale Blvd. -
Sageking to Yost Rd.
Key Map
616F |
Joint participation with the City of
Pearland in the construction of a 4-lane
concrete roadway and
bridge with storm
sewers and traffic signals. |
Complete |
2007 |
Scott Street
From BW8 to Almeda -Genoa Road
Key Map 573Y |
Design/Construct 4-lane
divided concrete roadway. |
Preliminary
Engineering
|
2011 |
Scott Street
From Almeda -Genoa Road to Orem
Key Map 573L |
Design/Construct 4-lane
roadway
with
storm sewers. |
Design
|
2011 |
South Belt
Pedestrian Bridge
Key Map 616Q |
Design / Construct
Pedestrian Bridge. |
Design |
2011 |
South Gessner
From BW8 to 0.45 miles along S. Gessner
Key Map 570 F |
Re-construct existing 4-lane
concrete roadway with
new traffic signal. |
Design
|
2011 |
Stafford/Staffordshire Road
(Riceville School Road)
From BW8 to Fort Bend C/L)
Key Map 570E |
Widen existing 2-lane asphalt roadway to a
4-lane
concrete roadway. |
Construction |
2011 |
|
|
|
|
|